Thank you again for your continued patience and cooperation through our renovation. Remember to check the project website updatesatthe643.com for more information including virtual tours, high performance and technology being used on the 643 project. You can also use HoloBuilder to see 360 photo updates of the progress work.


Starting Monday, 4/24 the main building entrance will be open again. Doors from the parking lot and the sidewalk will be accessible. The temporary entrance will no longer be in use. See attached logistics plan.


This Week

  • Finished storefront

  • Continued installation of reception desk and top

  • Installed carpet in vestibule

  • Installed card readers, cameras and doorbells

  • Started planter installation in lobby

  • Installed glass handrail at first floor

  • Finishing resurfacing the exterior ceiling

  • Mechanical commissioning


This Weekend

  • Phase 3 will begin

  • Main building entrance will reopen

  • Temporary entrance will be removed and infilled


Next Week

  • Exterior painting

  • Metal column covers will be installed

  • Infill Phase 2 temporary entrance, exterior wall and interior conference room

  • Install bike racks

  • Start final cleaning throughout the space

  • Start architect punch list

  • AV commissioning work


For those that park in the surface lot, deliveries will continue for the renovation (furniture, scaffolding, appliances, etc.) and the delivery trucks may be temporarily parked in the surface parking lot. Your patience is appreciated during this time. Thank you!


Below are some activities taking place next week as we continue to stay on schedule.

General reminders

  • Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.

  • All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.


 
 
 


Thank you again for your continued patience and cooperation through our renovation. Remember to check the project website updatesatthe643.com for more information including virtual tours, high performance and technology being used on the 643 project. You can also use HoloBuilder to see 360 photo updates of the progress work.


For those that park in the surface lot, deliveries will continue for the renovation (furniture, scaffolding, appliances, etc.) and the delivery trucks may be temporarily parked in the surface parking lot. Your patience is appreciated during this time. Thank you!


This Week

  • Continuing scaffolding on the stairs

  • Continuing the installation of storefront vestibule on the first floor

  • Finishing wood risers and stairs

  • Continuing installation of precast terrazzo on display steps

  • Installing felt wall panels

  • Started onsite AV work

  • Started mechanical test and balancing

  • Conference room tables were delivered

  • Resurfacing of the exterior ceiling started

  • Pantry appliances were delivered and installed

  • Beginning installation of the new fire alarm panel ongoing

  • Continuing exterior masonry cleaning and repairs


Next Week

  • Scaffolding will come down on Monday

  • Finish storefront

  • Install reception desk and top

  • Install carpet in vestibule

  • Install card readers, cameras and doorbells

  • Start planter installation in lobby

  • Exterior painting will begin

 
 
 