Thank you again for your continued patience and cooperation through our renovation. Remember to check the project website updatesatthe643.com for more information including virtual tours, high performance and technology being used on the 643 project. You can also use HoloBuilder to see 360 photo updates of the progress work.



This Week

  • Started installation of countertops in pantry

  • AV Cabling has started

  • Solid surface perimeter windowsills were installed on the second floor

  • Started ceiling framing on the first floor

  • Start-up of the exterior mechanical condensing unit

  • Continued to install second floor roller shades

  • Tread and riser installation is ongoing


Next Week

  • Ceiling close-up inspection for First Floor Phase 2

  • Drywall/taping will start in lobby

  • Install remaining metal panels on the exterior

  • Ceramic tile backsplash installation in second floor pantry

  • Vending shelf installation will begin


General reminders

  • During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.

  • Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.

  • Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.

  • All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.