Weekly progress updates 3.10
- agertz
- Mar 16, 2023
- 1 min read
Thank you again for your continued patience and cooperation through our renovation. Remember to check the project website updatesatthe643.com for more information including virtual tours, high performance and technology being used on the 643 project. You can also use HoloBuilder to see 360 photo updates of the progress work.
This Week
Started installation of countertops in pantry
AV Cabling has started
Solid surface perimeter windowsills were installed on the second floor
Started ceiling framing on the first floor
Start-up of the exterior mechanical condensing unit
Continued to install second floor roller shades
Tread and riser installation is ongoing
Next Week
Ceiling close-up inspection for First Floor Phase 2
Drywall/taping will start in lobby
Install remaining metal panels on the exterior
Ceramic tile backsplash installation in second floor pantry
Vending shelf installation will begin
General reminders
During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.
Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.
Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.
All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.

















Comments