Weekly Progress Updates 12.9.22

  • agertz
  • Dec 9, 2022
  • 1 min read

ree

Thank you again for your continued patience and cooperation through our renovation. I encourage you to check our project website updatesatthe643.com for more information including virtual tours, high performance and technology being used on the project. New progress photos are attached and you can also use HoloBuilder to see updates of the progress work.




This Week

  • Completed fireproofing of steel on the second floor

  • Tile backer drywall in the restrooms

  • Continuing to frame soffits and ceilings on the second floor

  • Continuing drywall taping

  • Continuing overhead MEP rough-in on the first floor

  • In-wall pantry plumbing testing and insulating

  • Prepping the first-floor steel for framing and spray insulation


Saturday

  • The office will be closed this Saturday, 12/10, for waterproofing work.


Next Week

Below are some activities taking place next week as we continue to stay on schedule.

  • Drywall taping will continue

  • Framing soffits and ceiling on the second floor will continue

  • Last concrete pour on the first floor

  • Start and finish spray proofing on the first floor

  • Start cold-form metal framing of the exterior wall

  • Start ceramic tile prep on the second-floor restrooms


General reminders

  • During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.

  • Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.

  • Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.

  • All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.