Weekly Progress Updates 12.2.22
- agertz
- Dec 2, 2022
- 1 min read

Thank you again for your continued patience and cooperation through our renovation. I encourage you to check our project website updatesatthe643.com for more information including virtual tours, high performance and technology being used on the project. You can also use HoloBuilder to see updates of the progress work.
This Week
Poured first-floor topping concrete
Started drywall on the second floor
Continuing with overhead MEP rough-in
Insulating the in-wall plumbing
Detailing on the monumental stair
Saturday
The office will be closed this Saturday, 12/3, for plumbing work.
Next Week
Below are some activities taking place next week as we continue to stay on schedule.
Fireproofing the steel
Tile backer drywall in the restrooms
Will start framing soffits and ceilings on the second floor
Will start drywall taping
Will start overhead MEP rough-in on the first floor
General reminders
During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.
Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.
Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.
All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.