Thank you again for your continued patience and cooperation through our renovation. Remember to check the project website updatesatthe643.com for more information including virtual tours, high performance and technology being used on the 643 project. You can also use HoloBuilder to see 360 photo updates of the progress work.





This Week

  • Stair tread adhesion testing completed

  • Continued installation of stair treads

  • Started framing for the new entryway

  • First floor overhead mechanical rough-in ongoing

  • Exterior condenser unit piping and insulation work

  • Installed marker boards


Next Week

  • Backsplash tile in the pantry will be installed

  • Solid surface perimeter windowsills will be installed on the second floor

  • Starting ceiling framing on the first floor

  • Start-up of the exterior mechanical condensing unit

  • Second floor roller shades will be installed


General reminders

  • During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.

  • Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.

  • Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.

  • All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.