Thank you again for your continued patience and cooperation through our renovation. Remember to check the project website updatesatthe643.com for more information including virtual tours, high performance and technology being used on the 643 project. You can also use HoloBuilder to see 360 photo updates of the progress work.


We’re looking forward to everyone joining the 643 Ribbon Cutting on June 1 from 10:00am – 12:00 pm. Please respond to the Save the Date I sent out earlier this week.


This Week

  • Metal column covers being installed

  • Infill Phase 2 temporary entrance, exterior wall and interior conference room

  • Installed bike racks

  • Final cleaning on the second floor is complete

  • Architectural punch of first floor happening on Friday

  • Started architect punch list

  • AV commissioning work is ongoing

  • Demountable partitions and new carpet in new huddle rooms will be installed

  • Signage will be installed


This Weekend

  • Barricades and floor protection in lobby will be removed

  • The lobby will be cleaned

  • The storage area in the parking lot will be condensed


Next Week

  • Fire department and final inspections

  • First floor architectural punch completion and cleaning

  • Start reception desk switch

  • Install Bevi machine


For those that park in the surface lot, deliveries will continue for the renovation (furniture, scaffolding, appliances, etc.) and the delivery trucks may be temporarily parked in the surface parking lot. Your patience is appreciated during this time. Thank you!


General reminders

  • Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.

  • All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.