Weekly Progress Update 2/10/23
- agertz
- Feb 13, 2023
- 1 min read
The office will be closed the weekend of 2/18-2/19 to continue lobby work. There will be a new employee entrance starting Monday, February 20th. More details to follow.
This Week
Stair scaffolding was removed.
Millwork delivery.
Door delivery.
Continued installing carpet.
Finished glass curtainwall install on the first floor.
Started installing roof curbs for mechanical equipment.
Delivered and install operable partition.
Wood floor prep work has started.
Next Week
Millwork will be on-going.
Interior demountable partitions will be installed.
Exterior metal panels will be starting.
Wood floor installation will start on the second floor.
Preparation for relocation of employee entrance.
General reminders
During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.
Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.
Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.
All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.

















Comments