From May to Now

  • agertz
  • Sep 20, 2024
  • 1 min read

Milestones:

  • Large cranes on site to place equipment and materials

  • The terrace field has been set on the 8th floor and we continue to work on the north elevation

  • The new mechanical units were started in the building

  • Millwork and furniture have begun to arrive onsite.

  • Furniture is installed on floors 4-7 with level 3 and 8 coming in the upcoming weeks

  •  IT has started to install monitors in the workstations and plans for the privacy planters are also progressing




ree

Up & Coming

·       Submission for the Certificate of Occupancy,

·       Resurface the main entrance, surface lot, basement lot and ramp. 

·       Finish touches on terrace pavers

·       Complete ComEd upgrades

·       Installation of glass panels in the parapet

·       Installation of sunshade sail

·       Commissioning AV  

·       Complete raised flooring to the terrace

Exciting developments are underway for the building's exterior! The removal of the Pepper "P" is just the beginning. We're planning to paint the brick and are collaborating with Ziken Signage on new signage, which will give the building an updated facelift.