Thank you again for your continued patience and cooperation through our renovation. Remember to check the project website updatesatthe643.com for more information including virtual tours, high performance and technology being used on the 643 project. You can also use HoloBuilder to see 360 photo updates of the progress work.




This Week

  • Ceramic tile backsplash installed in second floor pantry

  • Taping and first coat of paint on lobby ceiling completed

  • MEP ceiling trim started on first floor

  • Started restroom countertops and accessories installation

  • Started structure for screen wall condensing unit completed

  • Final paint on the second floor started

  • Started piping for first floor car chargers


Next Week

  • Begin terrazzo on the first floor

  • Install the final plumbing trim on the second floor

  • Complete final painting of second floor

  • Install pantry island top

  • Complete work on the screen wall outside


General reminders

  • During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.

  • Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.

  • Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.

  • All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.



 
 
 

Happy St. Patrick’s Day!




Thank you again for your continued patience and cooperation through our renovation. Remember to check the project website updatesatthe643.com for more information including virtual tours, high performance and technology being used on the 643 project. You can also use HoloBuilder to see 360 photo updates of the progress work.


This Week

  • Started installation of pantry countertops

  • Tread and riser installation is ongoing

  • Ceiling close-up inspection for First Floor Phase 2

  • Drywall/taping started in lobby

  • Vending shelf installation completed


Next Week

  • Ceramic tile backsplash installation in second floor pantry

  • Taping and first coat of paint on lobby ceiling

  • MEP ceiling trim will begin on first floor

  • Starting restroom countertops and accessories installation

  • Starting structure for screen wall condensing unit

  • Final paint on the second floor


General reminders

  • During construction, parking spaces have been assigned. Please ensure that you use only your spot or park offsite.

  • Visitors will not be able to park in the lot and visiting employees should be prepared to find remote parking. Double parking will not be permitted.

  • Emergency issues related to the 643 renovations should be routed to Jack Brown at 847-338-4308.

  • All general building maintenance/engineering issues should still be sent to Tom Brannon at 847-609-7893.


 
 
 